Re: Single planned order requirement of Semi-finished & that  SFG is part of BOM of multiple line items of sale order

$
0
0

Hello,

 

This is not possible in standard SAP if you used Individual/coll. = 1 Individual requirement.

System will generate the planned orders for every individual sales order line item.

 

If you used Individual/coll. = 2 collective requirement with lot size as EX system will generate the planned orders for all the requirement on the day.  Please test with Individual/coll. = 2 collective requirement with lot size as EX

 

Best Regards,

R.Brahmankar