Hii Rami,
PPDS Optimizer, does consider source of supply Priorities, Bit it can;t move order from one source to others.
PPDS optmizer can move order from one mode priority to other mode priority with in a single source of supply ..
example : We run optimizer as resource as a selection and there are two resource . We do have two PDS for the below combination
PDS 1 : mat 1 , Resource 1 , Bom 1 (procurement priority 0)
PDS 2 : Mat 1 , resource 2, Bom 1 (Procurement priority 1)
Optimizer won';t be able to move order s from PDS 1 to PDS2 ..
Optimizer can move order if it is the below scenario:
PDS1 with Mode A: mat 1 , Resource 1 , Bom 1
PDS 1 with Mode B : mat 1 , Resource 2 , Bom 1..
Hope i have answered your query...