Re: PPDS Resource Constraint Planning for Multiple Source of supply

$
0
0

Hii Rami,

 

PPDS Optimizer, does consider source of supply Priorities, Bit it   can;t move order from one source to others.

 

PPDS optmizer can move order from one mode priority to other mode priority with in a single source of supply ..

 

example : We run optimizer as resource as a selection  and there are two resource . We do have two PDS  for the below combination

 

PDS 1 : mat 1 , Resource 1 , Bom 1 (procurement priority 0)

PDS 2 : Mat 1 , resource 2, Bom 1 (Procurement priority 1)

 

Optimizer won';t be able to move order s from PDS 1 to  PDS2 ..

 

Optimizer can move order if it is the below scenario:

 

PDS1 with Mode A: mat 1 , Resource 1 , Bom 1

PDS 1 with Mode B : mat 1 , Resource 2 , Bom 1..

 

Hope i have answered your query...

 

Regards

Debashis