Budget check for material price change

$
0
0

Hello Mentor, In our project, we have a requirement of budget check at MR21 (material price change). As a result, it is possible to control budget consumption within approved available budget. While executing transaction through MR21, system allows to post transaction even if insufficient budget in WBS.  At present system, control for budget check for WBS exists at all the level of budget consumption but it does not exist at MR21 level. Can you please advise, how I can do it, as standard SAP Availability control tolerance limit do not have any tolerance group for budget checking for material price change (MR21). Looking forward for your reply. Thanks, Amlan